Government Disburses Shs 373bn to SGR Project-Affected Persons as Malaba–Mayuge Corridor Hits 98% Acquisition

Government Acquires 2,108 Acres for SGR After Compensating 7,721 Landowners

Andrew Matege·News·

Share
Government Disburses Shs 373bn to SGR Project-Affected Persons as Malaba–Mayuge Corridor Hits 98% Acquisition

Government has paid Shs 373.07 billion to 7,721 project-affected persons, securing 98% of the Malaba–Mayuge SGR corridor as Turkish contractor Yapı Merkezi completes €75 million in preparatory works ahead of full construction.

The Government of Uganda has disbursed Shs 373.07 billion in land compensation to 7,721 project-affected persons (PAPs), clearing major right-of-way hurdles for the construction of the 272-kilometre Malaba–Kampala Standard Gauge Railway (SGR).

Briefing Parliament on Tuesday, November 17, 2026, the Minister of State for Works and Transport, Hon. Fred Byamukama, reported that the disbursements have enabled the state to acquire 2,108 acres out of the 3,536 acres required for the entire railway corridor. Out of a total 12,946 enumerated beneficiaries, 5,225 remain to be paid an outstanding balance of Shs 472.45 billion in subsequent phases.

Minister Byamukama highlighted that land acquisition is most advanced along the Malaba–Mayuge section, where approximately 98 percent of the continuous corridor has been secured, unlocking roughly 130 kilometres of unencumbered land ready for immediate civil works. He noted that compensation remains ongoing with priority accorded to construction-critical sections.

Updating lawmakers on contractor mobilization, Byamukama revealed that Turkish construction firm Yapı Merkezi concluded a €75 million (approximately Shs 341.63 billion) Limited Notice to Proceed (LNTP) in October 2026, following its commencement on May 14, 2025. The preparatory phase covered topographical surveys, geotechnical investigations, and the procurement of earth-moving machinery, reducing technical risks ahead of full financial closure and the issuance of a full Notice to Proceed. Once completed, the line will link Uganda directly to Kenya’s railway network and the Port of Mombasa.

During the ensuing plenary debate, Shadow Minister for Works and Transport Hon. Asinansi Nyakato criticized the protracted compensation delays, arguing that sluggish disbursements have inflated overall project costs. She also pressed the ministry to clarify how climate change risks are factored into the railway budget in line with parliamentary resolutions. In response, Byamukama confirmed that Shs 11 billion has been ring-fenced for environmental safeguards, with room to scale up the allocation if required.

Meanwhile, Kassanda County South MP Hon. Abdul Bisaso raised alarm over alleged encroachments and unannounced demolitions carried out by Uganda Railways Corporation (URC) staff, claiming that residents holding valid land titles outside railway land were being targeted without engaging local leaders. He petitioned the ministry to dispatch surveyors for a formal boundary-opening exercise.

Minister Byamukama defended the clearances in Kassanda, stating that the demolished structures sat inside the gazetted railway reserve and that the enforcement prevented the state from paying fraudulent compensation for illegal developments on public right-of-way. He nevertheless assured the House that joint boundary-opening exercises will be conducted wherever corridor boundaries are contested by residents.